Construction of a biomass heating plant in Mali Zvornik

The Public Sector Projects Implementation Unit Ltd. Belgrade conducted professional supervision on the construction of a biomass and gas-fired thermal boiler facility with a total capacity of 4.8 MW, the construction of a district heating pipeline with a total length of 2.4 km, as well as the replacement of transfer substations in 30 facilities within the municipality of Mali Zvornik.

Project implementation period: 2020 – 2022