Science and Technology Park in Novi Sad, Phase II

The Science and Technology Park in Novi Sad was opened on January 29, 2020. The Public Enterprise managed the construction of the project. This is also the largest facility overseen by the Public Enterprise, which handled both the project management and professional supervision.

The constructed facility has a gross area of 31,345 square meters. On 10,000 square meters, 3,000 students and 400 professors, associate professors, and assistants from the Faculty of Technical Sciences have access to state-of-the-art working conditions.

The construction of the Science and Technology Park is part of the Research and Development project. The construction of Phase II/1 is financed by a loan from the European Investment Bank and funds from the University of Novi Sad - Faculty of Technical Sciences.

The Science and Technology Park is a joint project of the Government of the Republic of Serbia and the Provincial Government, with the support of the City of Novi Sad and the Faculty of Technical Sciences.

Science and Technology Park in Novi Sad, Phase II/2a

Execution of construction and construction-craft works to bring part of the facility and the garage of the Technology Park in Novi Sad to functional condition. The total value of the construction for Phase II and II/2a is 23,635,518 euros.

Tenders

IOP /3 -2014, Construction of the "Science Technology Park" facility in Novi Sad (Phase II/1)

Public calls

Questions & Answers

Attachment 6 - Recuperators - Drawings and Technical Data

Download

Notices of Procedures Carried Out

Notification of the concluded contract (1)

Download

Other information

012 8.1 Heating and Air-Conditioning_BoQ + CE srb eng update No1 20150323

Download

O /07 -2015 /U – Procurement of the service of development of the plan of preventive measures and the services of the design coordinator and coordinator for the execution of works on the construction of the "Science and Technology Park" facility in Novi Sad

Public calls

Invitation for Submission of Bids NTP NS-signed

Download

Data from the tender documents

Notices of Procedures Carried Out

Notification of the concluded contract NTP NS

Download

IOP3 -2014 /NP – International Negotiated Procurement Procedure – service of amending the design and technical documentation for the execution of works on the construction of the facility "Technology Park of the University of Novi Sad" – phase II/1 and contracting of eight positions of modified works

Notices of Procedures Carried Out

Announcement of Suspension of Public Procurement Procedure

Download

Notice of Initiation of Negotiated Procedure

Download

Negotiated procedure for the procurement of additional (unforeseen) works on the construction of the "Science Technology Park" Novi Sad (phase II/1)

Public calls

Data from the tender documents

Notices of Procedures Carried Out

Negotiated procedure for the procurement of additional (unforeseen) works on the construction of the "Science Technology Park" Novi Sad (phase II/1)

Public calls

Notice of Initiation of Proceedings (1)

Download

Data from the tender documents

Execution of construction and construction-craft works for bringing into functional condition a part of the building and garage of the Technology Park in Novi Sad (Phase II/2 and Phase II/2a)

Public calls

Data from the tender documents

Questions & Answers

Notices of Procedures Carried Out

Other information

Notification of the submitted request for protection of rights

Download

Decision on the submitted request for protection of rights - Republic Commission

Download

Information on the Public Opening of Financial Offers

Download